This week we should see the end of the second floor elevation. This wall won't look like this for long, the bricks, (CMUs) will be covered over in the end. Steel is coming in very soon to brace the walls, and form our mezzanine and roof. In about 4 weeks, we should be indoors, in a nice, dry workspace. Below is the progress made over the last few days of the second floor.
East Wall complete.
East and North wall complete.
West wall begins.
West wall rises.
South and West wall almost complete. This is 8/10, and later today, we should see the walls complete and tomorrow the scaffolding removed.