The Slab
I've learned many new construction phrases when talking to our contractor and architects. One, is that they refer to the base concrete as a slab. That being said, we lay our new slab down beginning on Monday, 7/10. On Friday, 7/7 they began work on a portion of recessed concrete that will be directly in front of the stage. It's the first piece that's been added in that will actually be visible on the final product. Granted, it will be covered with carpet, but still. The floor recession, or the pit, is dug.
Keep coming back for more updates on the Slab over the next week.
7/13 we buried the bar and restroom plumbing.
7/14: What vault?
Monday we begin a new phase of construction in the eastern half. Steel and Masonry. No more digging on this half. (Except for the water main) We go up from here!