Two Weeks into Demo
We begin the construction journal two weeks after our Groundbreaking. We have spent time demoing the building. Ray, the foreman, and his team worked very quickly to get the front half of the building stripped of it's white tile, walls cleared out, and then... they removed the roof. The second half of the building was a little more challenging. There were steel pieces on the ceiling that had to be removed, and the cinder block walls had to come down. Some of them structural, so support had to come in, as they chipped away at them. We don't need the whole roof to come down. A water main challenge was presented, but it shouldn't hold too much back.
We have set up a temporary office at La Colombe coffee in the meantime, making meetings more powerful with draft lattes, and "Black and Tans". We should be seeing the plumbing, and concrete guys within the next week.